Nicholson In The Neighborhood: Virginia’S North Hill ProjectBy Dominic Ammon, Mark Rothbauer, Paul Landers P. E.
Across the Potomac River from the location of the DFI47 Annual Conference (October 2022), in Alexandria, VA, two large permanent anchored walls with a decorative shotcrete face were recently construct
Oct 1, 2022
-
Drilled Shaft Design, Testing and Construction in New Jersey Turnpike - Case StudiesBy Abu B. Siddique, Anthony S. Crincoli
"The New Jersey Turnpike Section 2 widening program consisted of widening between Interchange 6 in Mansfield Township, Burlington County and Interchange 9 in East Brunswick Township, Middlesex County.
Jan 1, 2015
-
Secant Pile Barrier Wall Overlap, Thickness, and Position at the U.S. Army Corps of Engineers Wolf Creek Dam, Jamestown, KYBy Bernard B. Vannoy, Howard W. Gault, Ramesh Bobba
"Treviicos-Soletanche Joint Venture (JV) and the US Army Corps of Engineers (USACE) have installed a 3800-foot long, 275-foot deep and minimum 2-foot wide secant pile barrier wall at Wolf Creek Dam in
Jan 1, 2015
-
Full Scale Uplift Load Testing of Micropiles in Cohessionless SoilBy M. Hesham El Naggar, Maged A. Abdlrahem
"Hollow bar micropiles have constructional advantages such as: fast and low-noise and low vibration installation process and small installation equipment, which allow access to tight places. In additi
Jan 1, 2016
-
Effects Of Self-Weight On Thermomechanical Response Of Energy PilesBy Arash Saeidi Rashk Olia, Dunja Perić
The increasing demand for renewable energy has attracted attention to energy geostructures as means of extracting clean geothermal energy from the ground. To further advance the understanding of soils
Oct 1, 2022
-
Innovative Use of an Active Soil Nail Wall in Lieu of Pit Underpinning for a Historic BuildingBy Tai Luu, Maxim C. Schisler, Yaser Taheri
The Stevens Gateway Project is an expansion of the Stevens Institute campus overlooking the Hudson River in Hoboken, NJ. The plans call for 90,000 ft2 (8360 m2) of new classroom, research, and student
Jan 1, 2019
-
Caisson Foundations For Mississippi River Bridges In The New Orleans Area (2e66a216-6dc8-4479-804e-25f5836f407e)By William B. Conway
This paper will describe the large caisson pier foundations for four of the bridges crossing the Mississippi River in the New Orleans area; and will discuss some of the unusual problems encountered du
May 11, 2007
-
Acrylamide Grouting: Successfully Controlling Groundwater from Canada to South AmericaBy Daniel Magill, Jim Gentry
"Acrylamide chemical grout (C3H2NO) has been successfully used for over 50 years to control groundwater and stop infiltration. This paper will address three unique projects involving the control of gr
Jan 1, 2017
-
Determination of Initial Stiffness of Drilled Shafts for the Analysis of Settlements under Service LoadsBy Carlos A. Prato, Federico Pinto
"ABSTRACTThe design of drilled shafts often incorporates large factors of safety, for which settlements under service loads are highly influenced by the initial elastic stiffness. In the case of group
Jan 1, 2014
-
RD Pile Wall – A Water Tight Retaining Wall StructureBy Antti J. Perala, Teemu J. Yli-Kovero
"Efficient use of land is constantly requiring more underground construction. Minimized execution time and disturbance to surroundings and nearby structures are essential benefits for all construction
Jan 1, 2017
-
On Driven Piles In The Arabian Gulf: Imperfections, Potential Challenges, And Lessons LearnedBy Waddah Akili
The demand on pile installation in the offshore of the Arabian Gulf has, over the last two decades, experienced unprecedented boom, triggered by the construction of platforms, to help facilitate the p
-
Implant Foundations – Press-in Piling Method for Urban ConstructionBy Tsunenobu Nozaki
"Basically, the “Press-in Piling Method” was invented to eliminate construction nuisances, such as noise and vibration which have been serious unsolved problems for advancing societies over a long tim
Jan 1, 2015
-
Analysis of Laterally Loaded Free-Head Pile Groups in SandBy Ashraf M. Eid
Most research dealing with the problem of laterally loaded piles has been the response of individual piles subjected to lateral loads and/or bending moments. However, piles are seldom used individuall
Jan 1, 2005
-
Construction Of A Bicycle And Pedestrian Path West Of The Henry Hudson PWYBy David Coleman
This paper presents a case history involving the installation of drilled in piles with rock sockets for the Bicycle and Pedestrian Path project located west of the Henry Hudson Parkway within the Rive
-
New Findings on the Capacity of Connections between Micropiles and Existing FootingsBy João Veludo, Eduardo Júlio, Helen D. Robinson, Jesús E. Gómez
"Utilization of micropiles for structural retrofit requires connection of the micropiles to the footings of the existing structure. Almost ten years ago, an experimental research effort was carried ou
Jan 1, 2015
-
Execution Example of the Expanded Dry Jet Mixing (EX-DJM) Method (71db6e71-57a4-4d54-81bc-d746d501291d)By Kiyotaka Ohno, Nobushige Yasuoka, Yosuke Hioki
"The diameter of improved columns adopted by the original DJM Method had been 1000 mm, however, in order to comply with the social need for construction cost reduction, the Expanded Dry Jet Mixing (EX
Jan 1, 2015
-
Grouted Micropiles for Foundation Remediation in Expansive Soil (8th Michael W. O?Neill Lecture)By John D. Nelson
Foundation underpinning is a common component of remediation schemes for distressed foundations on expansive soils. For many applications in expansive soil, micropiles have distinct advantages over ot
Aug 1, 2013
-
The Berkeley Art Museum: Using Deep Foundations to Repurpose a Historical BuildingBy Timothy Nelson, Simon Burnworth
"The University of California’s new Berkeley Art Museum and Pacific Film Archive will showcase a collection of art and film in a facility that pairs an existing 1930s-era printing press facility with
Jan 1, 2017
-
Cement Deep Soil Mixing Shear Wall Stabilization Calaveras Dam Replacement Project, CaliforniaBy Michael Forrest, John Roadifer, Glen Gorski
"The Calaveras Dam Replacement Project (CDRP) requires large disposal sites to store excess excavated materials that could not be utilized for dam construction. Because of access restrictions during d
Jan 1, 2015
-
Foundation Stabilization of the Morris Island Lighthouse"The Morris Island Lighthouse (MIL) is located between the jetties leading to the Charleston Harbor and Folly Beach, S.C. The present structure is the third lighthouse to occupy this location. The fir